Total Knowledge Areas remain same : 10
- Pmbok 5’s Project management processes Description : 47
- Pmbok 6’s Project management processes Description : 49
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)Sixth Edition
No. | Areas | Pmbok 5’s Descriptions | Pmbok 6’s Descriptions | Remarks |
1 | Knowledge Areas | Project Integration Management | Project Integration Management | |
Processes Descriptions | Develop Project Charter | Develop Project charter | ||
Processes Descriptions | Develop Project Management Plan | Develop Project Management Plan | ||
Processes Descriptions | Direct and Manage Project Work | Direct and manage Project work | ||
Processes Descriptions | Manage Project Knowledge | a New Processes Descriptions at Pmbok 6th | ||
Processes Descriptions | Monitor and Control Project Work | Monitor & Control Project Works | ||
Processes Descriptions | Perform Integrated Change Control | Perform Integrated change control | ||
Processes Descriptions | Close Project or Phase | Close Project or phase | ||
2 | Knowledge Areas | Project Scope Management | Project Scope Management | |
Processes Descriptions | Plan Scope Management | Plan Scope Management | ||
Processes Descriptions | Collect Requirements | Collect requirements | ||
Processes Descriptions | Define Scope | Define scope | ||
Processes Descriptions | Create WBS | Create WBS | ||
Processes Descriptions | Validate Scope | Validate Scope | ||
Processes Descriptions | Control Scope | Control Scope | ||
3 | Knowledge Areas | PROJECT TIME MANAGEMENT | Project Schedule Management | Changed description |
Processes Descriptions | Plan Schedule Management | Plan Schedule Management | ||
Processes Descriptions | Define Activities | Define Activities | ||
Processes Descriptions | Sequence Activities | Sequence Activities | ||
Processes Descriptions | Estimate Activity Resources | Moved to Project Resources | ||
Processes Descriptions | Estimate Activity Durations | Estimate Activity Durations | ||
Processes Descriptions | Develop Schedule | Develop Schedule | ||
Processes Descriptions | Control Schedule | Control schedule | ||
4 | Knowledge Areas | PROJECT COST MANAGEMENT | Project Cost Management | |
Processes Descriptions | Plan Cost Management | Plan cost Management | ||
Processes Descriptions | Estimate Costs | Estimate costs | ||
Processes Descriptions | Determine Budget | Determine Budget | ||
Processes Descriptions | Control Costs | Control Cost | ||
5 | Knowledge Areas | PROJECT QUALITY MANAGEMENT | Project Quality Management | |
Processes Descriptions | Plan Quality Management | Plan Quality Management | ||
Processes Descriptions | Perform Quality Assurance | Manage Quality | Changed description | |
Processes Descriptions | Control Quality | Control Quality | ||
6 | Knowledge Areas | PROJECT HUMAN RESOURCE MANAGEMENT | Project Resource Management | Changed description |
Processes Descriptions | Plan Human Resource Management | Plan resource Management | Changed description | |
Processes Descriptions | Estimate Activity resources | from Project Time Management | ||
Processes Descriptions | Acquire Project Team | Acquire Resources | ||
Processes Descriptions | Develop Project Team | Develop Team | ||
Processes Descriptions | Manage Project Team | Manage team | ||
Processes Descriptions | Control Resources | a New Processes Descriptions at Pmbok 6th | ||
7 | Knowledge Areas | Project Communication Management | Project Communication Management | |
Processes Descriptions | Plan Communications Management | Plan Communication Management | ||
Processes Descriptions | Manage Communications | Manage Communications | ||
Processes Descriptions | Control Communications | Monitor Communication | Changed description | |
8 | Knowledge Areas | Project Risk Management | Project Risk Management | |
Processes Descriptions | Plan Risk Management | Plan risk management | ||
Processes Descriptions | Identify Risks | Identify risk | ||
Processes Descriptions | Perform Qualitative Risk Analysis | Perform qualitative risk analysis | ||
Processes Descriptions | Perform Quantitative Risk Analysis | Perform quantitative risk analysis | ||
Processes Descriptions | Plan Risk Responses | Plan risk responses | ||
Processes Descriptions | Implement risk responses | a New Processes Descriptions at Pmbok 6th | ||
Processes Descriptions | Control Risks | Monitor risks | Changed description | |
9 | Knowledge Areas | Project Procurement Management | Project Procurement Management | |
Processes Descriptions | Plan Procurement Management | Plan Procurement | ||
Processes Descriptions | Conduct Procurements | Conduct Procurements | ||
Processes Descriptions | Control Procurements | Control Procurements | ||
Close Procurements | Deleted at PMBOK 6th, accommodate on Close Project | |||
10 | Knowledge Areas | Project Stakeholder Management | Project Stakeholder Management | |
Processes Descriptions | Identify Stakeholders | Identify Stakeholder engagement | ||
Processes Descriptions | Plan Stakeholder Management | Plan stakeholder engagement | ||
Processes Descriptions | Manage Stakeholder Engagement | Manage stakeholder engagement | ||
Processes Descriptions | Control Stakeholder Engagement | Monitor Stakeholder engagement | Changed description |